missing schedule line after creation of contract + LPA + LP and source list
Analysys : see ticket INC-106647
item : TPE9159
In MRP 2, you have Planned Delv. Time of 84 days
first : When you start MRP calculation, a purchase requisition will be placed according the planned delivery time
Ex : with current data in all contract
second : schedule line generation
the data of validity start and validity end aren’t correct in the contracts and source list
all contracts have been created with validity end of 31.03.2021 but the planned delivery time is 84 days, so the requirement will be post in April.
In order to be consistent, you have to update for all contracts and source list the same date in 30.04.2021 (minimum). according internal procedure put 31.12.9999
ME32K
ME32L
ME32L
ME01
Restart MRP calculation with MD02
A schedule line is generated